Formwork
Formwork is used to hold the concrete in any
structural element before hard it. The weight of the wet concrete is higher
than the dry concrete. Therefore the formwork should be strong enough to carry
the load of the wet concrete. So also formwork should be free of voids and
concrete or grout should not be going out from the formwork. So also it should
be straight enough to maintain the shape of the structural element and can be
withstand against the vibration of the equipment used. Therefore the form work
is very important in the concreting works.
Definition:
§ As
a structure,
§ Temporary
which is designed to contain fresh fluid concrete.
§ Form
it into the required shape and dimensions.
§ Support
it until it cures sufficiently to become self supporting.
The term ‘formwork’ includes the actual material contact with the concrete, known as form face, and all the necessary associated supporting structure.
REQUIREMENTS
OF A GOOD FORMWORK SYSTEM
§ How formwork can be erected and
de-shuttered fast.
§ How good concrete quality and
surface finish can be achieved.
§ What is the optimum stock of
formwork required for the size of work force, the specified time schedand flow of materials.
§ What is the overall cost savings
that can be achieved using the right type of formwork.
§ How safety can be improved for the
site personnel.
To successfully
carry out its function, formwork must achieve a balance of following
requirements:
·
Containment: formwork must be capable of shaping
and supporting the fluid concrete until it cures.
· Strength: formwork must be capable of
safely withstanding without distortion or danger the dead weight of the fluid
concrete is placed on it, labour weight, equipment weight and any environmental
loadings.
· Resistance to leakage: all joints in form
work must be either close fitting of covered with form tape to make them grout
tight. If grout leakage occurs the concrete Will leak at that point. Leakages
cause honeycombing of the surface.
· Accuracy: formwork must be accurately set
out so that the resulting concrete product is in a right place and is of
correct shape and dimensions.
· Ease of handling: form panels and units
should be designed so that their maximum size does not exceed that which can be
easily handled by hand or mechanical means. In addition all formwork must also
be designed and constructed to include facilities for adjustments, leveling,
easing and striking without damage to the form work or concrete.
·
Finish and reuse potential: the form face
material must be selected to be capable of consistently imparting the desired
concrete finish (smooth, textured, featured or exposed aggregate etc.) At the
same time it should also achieve the required number of reuse.
·
Access for concrete: any formwork
arrangement must be provide access for placing of the concrete. The extent of
this provision will be dependent on the ease of carrying out the concrete
operations.
·
Economy: all the formwork is very
expensive. On average about 35% of the total cost of any finished concrete unit
or element can be attributed to its formwork; of this just over 40% can be
taken for material for formwork and 60% for labour. The formwork designer must
therefore not only consider the maximum number of times that any form can be
reused, but also produce a design that will minimize the time taken for
erection and striking.
No
|
Description of structural member
|
Period of time
|
1
|
Walls, columns and vertical sides of beams
|
1
to 2 days
|
2
|
Slabs (props left under)
|
3
days
|
3
|
Beam soffits (props left
under)
|
7
days
|
4
|
Removal of props to slabs
|
|
(a) For slabs spanning u pto 4.5
m
|
7
days
|
|
(b) For slabs spanning over 4.5 m
|
14
days
|
|
5
|
Removal of props to beams and
arches
|
|
(a) Spanning up to 6 m
|
14
days
|
|
(b) spanning over 6 m
|
21
days
|
|
6
|
Props to cantilever
|
28
days
|
7
|
Beam sides, walls & columns (unloaded)
|
24
hours
|
8
|
Slab (need to provide props)
|
4
days
|
Table
show : Duration taken for removal of formwork
TYPES OF FORMWORK
There are different types of formwork available for different purposes.
Generally, the formworks for vertical concreting are called wall forms and
those for horizontal concreting are called slab or floor forms. The various
types of formwork available today in the market are discussed in detail.
·
Traditional
formwork
·
Climbing
formwork
·
Sliding
formwork or slip forming
·
Permanent
formwork.
·
Special
forms
·
Table
form
·
Ganged
panel form
·
Tunnel
form
No comments:
Post a Comment